MAY 4, 2014

 

It’s been a week since the last update and a lot of the exterior work has been completed.  The 4’x8’ siding panels have gone up over the garage and around the front porch.  After a few complications with the staining work of these panels, we were finally ready to install them.  Each piece was precisely cut to fit snuggly around the entry and drilled, before being applied to the exterior, to maintain a consistent nailing pattern.  Since the exterior is nearing completion there is only one set of scaffolding remaining, and excavations can commence next week.

 

The flooring has been installed downstairs!  We still need to sand and put on a coat of polyurethane but a lot of progress was made within the past week. The trim work and painting upstairs is close to completion.  The details of the interior are slowly coming along, including the addition of a linen closet upstairs.  Some of the cabinets are installed in the kitchen, upstairs and downstairs bathroom.  Hopefully the bedrooms will be completed this upcoming week and we can focus on the downstairs areas.

Street view of our house Cutting the floor boards Installing the cabinets Assembling the kitchen cabinets Installing the drywall Detail work in the beige bedroom SouthWest facades of the house Sanding and painting the interior doors Cutting the siding Applying the siding panels

APRIL 27, 2014

We have returned to the Oregon BILDS house this Spring term! There was a little work done during the break to continue the momentum, professionals were hired to install the drywall and apply the textured spray on the walls.  But on March 31st a new crew was introduced to the Oregon BILDS house.  Once everyone had become familiar with the design, site, and tools we quickly started to work.  We finished applying the horizontal strip siding on all facades of the house and began painting the exterior walls.

The interior details have commenced the first week of the term.  The walls were primed and painted an assortment of colors.  The crew has worked on the interior’s trim work for a couple of weeks and will hopefully install and paint all the trim work by next week.

The cabinet’s for the kitchen were recently purchased from IKEA and are ready for installation.  The simplicity and flushed cabinet doors give it a modern, sleek look.

The downstairs flooring will be 2’x8’ strips of OSB; each panel was cut down in the shop to ensure consistency and to remove the manufacturer’s edge coating.  A layer of flooring adhesive was troweled on beneath each flooring section.  This allows for less required nailing and for a more solid finished product.